EXAMPLE
 
 
Task NAME: BUILDING
START DATE: APRIL 2022
FINISH DATE JULY 2022
 
 

BUILDING MATERIALS
Total Workers Involved: 26 to 32 The 3 -4 months of construction on an average home requires this
many people. On average, it takes seven months to build a house from start to finish.
PREP External Materials Internal Materials
Prepare Construction Site and Pour Foundation, Complete Rough Framing, Complete Rough Plumbing, Electrical HVAC, Install Insulation, Complete Drywall and Interior Fixtures house Mud and, Clay bricks and Blocks, Sand, Stone, Thatch, Wood Floor System, Walls, Roof Systems are Completed, and sheathing Applied to Exterior Walls, Covered with Protective Wrap Light fixtures, outlets and switches are installed, and the electrical panel is completed. HVAC equipment is installed, and registers completed.
Sinks, toilets, and faucets are put in place.
Finish, Finish Interior Trim, Install Exterior Walkways and Driveway,
Install Hard Surface Flooring,
Timber, Cement, Fabric, Foam, Glass, Gypcrete Metal, Plastics.
Ceramic tile, vinyl and wood
Interior doors, baseboards, door casings, windowsills,
moldings, stair balusters and

 

Countertops; Complete Exterior Grading, Finish Mechanical Trims; flooring is installed as well as countertop. other decorative trim is installed, along with cabinets, vanities, and fireplace mantels
and surrounds

 
 
TASK NAME: IMSPECTION
START DATE: JULY 30TH 2022
FINISH DATE: JULY 30TH 2022
 
 
 

Phase Inspection Process
During the building process, there are three windows of opportunity in which you should take advantage of the recommendation to have a third-party inspector review and report on the quality of the craftsmanship and construction of your new home. In order to guarantee that major building flaws within your property are not hidden from view, the traditional 3-phase inspection technique is performed.
Pre-pour Foundation Inspection Two days before the day that the actual pour would take place. Because of this, the foundation will be much more likely to be ready for inspection. This provides the contractor with sufficient time to make any and all necessary modifications, or to postpone the day that the pour is scheduled to take place.
Framing Inspection Walk-through with a framework. During this stage of the construction process, the builder will attempt to guarantee that all of the previously discussed and agreed upon design criteria have been appropriately incorporated into the house.
Final Inspection The final inspection should be scheduled a few days before your scheduled walk-through with your builder. The final inspection is conducted as part of a real estate transaction. it is regulated by the local Real Estate Commission. The final inspection incorporates all the major systems in
the home.

 
 
 
 
 
 
 
 

COMMUNICATION PLAN & PROJECT SCHEDULE- HOME BUILD:
DESCRIPTI ON FREQUEN CY COMMUNICATI ON METHOD AUDIENCE
Kick off Meeting DAILY- 1ST OF THE SHIFT Team huddle, allocate tasks needed to be completed that day Architect, project draftsman, Contractor, workers, and
Stakeholder.
Project Team Meetings WEEKLY Email progress and tasks needing to be completed Contractor and Workers
Check- ins/Meeting Recap DAILY, WEEKLY, BI WEEKLY, AND MONTHLY Meetings, Check-ins, Daily emails, daily site walkthrough Architect, project draftsman, Contractor
Project Status meetings WEEKLY, BI WEEKLY, AND MONTHLY Weekly Meetings, for workers and contractors. Also, milestone emails. Architect, project draftsman, Contractor, workers, and
Stakeholder
Design review WEEKLY AND END OF PROJECT Meeting and Site walkthrough Architect, project draftsman, Contractor, workers, and
Stakeholder

 
 
 
 
 
References
Holmes, S. B. (2021, January 20). A step-by-step guide to the home building process. A Step-by- Step Guide to the Home Building Process. Retrieved November 11, 2021, from https://www.newhomesource.com/learn/step-by-step-guide-to-home-building-process/.
 

Week 6 Activity
We have updated our contact contact information. Text Us Or WhatsApp Us+1-(309) 295-6991